Client: Attero B.V., Moerdijk/NL

Revision of Line 1 + 2 for Attero Moerdijk, Netherlands

After approximately 18 months in operation, EnergieLink performed the revision of the dosing plunger and grate in the waste-fed heating plant. in Moerdijk. Due to extensive maintenance work on the firing technology and various ancillary works in the grate area, a high degree of flexibility, as well as precise planning of complex construction processes within a very tight time frame was required.

The solution: A 24-hour shift schedule, adapted to the requirements on site. The waste-fed heating plant in Moerdijk is one of the most energy- efficient plants of its category in the Netherlands, thus placing the operating company Attero with its total of 15 plants, among the best-established in the country.