MHKW Bamberg
This was a swift process: within two weeks, EnergieLink performed the complete substitution of the feed hopper at the Bamberg waste incineration plant.

Infos:
Design, planning and production of the components within five months. Two weeks and six employees for the on-site implementation - a satisfactory result:

With regard to the design of the new feed hopper, focus was on a wear- and temperature-resistant lining of the interior area, and the EMSR technique was implemented to ensure optimum monitoring of the system.

The design of the cooling system now features dual cooling. The entire piping was performed with V4A quality. Following completion of the inspection work, the system was hydraulically and electrically commissioned.

Period of idleness: three weeks. That's what we call fast quality.